September 24 – September 30, 2022 Progress
* Sites worked on this week: 1, 10, 12, 29, 51, 54, 55, 59, 60, 72, 82, 83, 85, 86, 87, 88, 90, 93, 102, 103, 104, 109, 111, 112, 115, 132, 142, 147, 149, 150, 151, 158, 163, 166, 177, 181, 194, 210, 224, 225, 229
* Completed site: See attached map
* Culvert sites repaired: 97, 193
* Totals sites: 244
* Ditches cleaned: 174.1 miles
* Roads temporarily graded: 106 Miles – Regraded roads after ditch works this week.
* Contractors working: 8
* Pieces of equipment: 22
* Urgent requests addressed: 3