October 1 – October 7, 2022 Progress

 

Sites worked on this week: 12, 29, 51, 54, 55, 60, 82, 84, 86, 87, 88, 90, 93, 97, 102, 103, 104, 109, 111, 112, 115, 122, 125, 132, 134, 147, 150, 151, 154, 158, 163, 166, 171, 177, 194, 210, 229

Completed site:  See attached map

Culvert sites repaired: 98, 133, 183, 185

Totals sites: 244

Ditches cleaned: 179.6 miles

Roads temporarily graded: 106 Miles – Regraded roads after ditch works this week.

Mile Road 26N b/t 3E-4E

Mile Road 5E, b/t 27N-30N

Mile Road 30N, b/t 5E-6E

Mile Road 3E, b/t 26N-28N

Mile Road 33N, b/t 1W-3W

Mile Road 21N, b/t Meridian Road -5E

Mile Road 3E, b/t 19N-21N

Mile Road 2E, b/t 21N-24N

Mile Road 20N, b/t 3W-5W

Contractors working: 9

Pieces of equipment: 24

Urgent requests addressed: 3