  • Sites worked on this week:  6, 7, 27, 28, 29, 31, 61, 73, 75, 81, 88, 90, 95, 127, 129, 155, 175, 176, 177, 180, 181, 182, 188, 196
  • Totals sites: 201
  • Ditches cleaned: 28.1 miles
  • Contractors working: 11
  • Pieces of equipment: 20
  • Urgent requests addressed: 11
  • Two additional contractors lined up for Monday and 7 additional pieces of equipment (North Rok – two crews)
  • On Monday we will also have a dedicated “Emergency Team” with mobile equipment to address urgent requests.