Ditch Cleaning was suspended from July 19 (Tues) to 21 (Thurs) due to landfills repair brought by heavy rains.
- Sites worked on this week: 10, 51, 59, 69, 80, 81, 82, 88, 89, 112, 122, 136, 145, 177, 213
- Completed site: None this week
- Culvert sites repaired: 2 – Site 112, 145
- Totals sites: 229
- Ditches cleaned: 98.25 miles
- Roads temporarily graded:
- Mile Road 2E, isolated sections
- Mile Road 21N b/w 3E-4E
- New crew starting July 25 dedicated to Mile Road 2E
- Contractors working: 18
- Pieces of equipment: 36
- Urgent requests addressed: 2
- EMO assessed 54 sites this week