Ditch Cleaning was suspended from July 19 (Tues) to 21 (Thurs) due to landfills repair brought by heavy rains.

  • Sites worked on this week: 10, 51, 59, 69, 80, 81, 82, 88, 89, 112, 122, 136, 145, 177, 213   
  • Completed site:   None this week
  • Culvert sites repaired: 2 – Site 112, 145
  • Totals sites: 229
  • Ditches cleaned: 98.25 miles

  • Roads temporarily graded:
    • Mile Road 2E, isolated sections
    • Mile Road 21N b/w 3E-4E
    • New crew starting July 25 dedicated to Mile Road 2E
  • Contractors working: 18
  • Pieces of equipment: 36
  • Urgent requests addressed: 2
  • EMO assessed 54 sites this week