Construction works down this week due to August 23 rains.

August 20 – August 26 2022 Progress

  1. Sites worked on this week: 7, 10, 14, 46, 59, 82, 88, 94, 97, 118, 132, 133, 143, 150, 151, 163, 164, 174, 181    
  2. Completed site:   Non this week
  3. Culvert sites repaired: 7, 14, 46, 133
  4. Totals sites: 230
  5. Ditches cleaned: 156.1 miles (90 ditch cleaning sites completed)
  6. Roads temporarily graded: 66 Miles
    1. Mile Road 33N b/t 1W-3W (ongoing for the week to assist with debris hauling)
  7. Contractors working: 15
  8. Pieces of equipment: 34
  9. Urgent requests addressed: 1