September 10 – September 16, 2022 Progress

  • Sites worked on this week: 10, 26, 46, 54, 57, 59, 72, 74, 76, 82, 83, 84, 85, 87, 88, 90, 93, 95, 102, 103, 104, 105, 109, 111, 122, 133, 135, 147, 150, 151, 154, 158, 174, 177, 182, 194, 224, 225
  • Completed site:  None this week
  • Culvert sites repaired: 26, 46, 74, 133, 182
  • Totals sites: 233

  • Ditches cleaned: 168.4 miles
  • Roads temporarily graded: 104 Miles,  
  • Mile Road 1W near PR 205
  • Mile Road 2E, b/t 22N-24N
  • Mile Road 3E, b/t 20N-21N
  • Mile Road 3E, b/t 26N-28N
  • Mile Road 3E, b/t 29N-30N
  • Mile Road 5E, b/t 26N-30N
  • Mile Road 21N, b/t 1E-4E
  • Mile Road 23N, b/t 2E-3E
  • Mile Road 26N, b/t 3E-4E
  • Mile Road 29N, b/t 2E-3E
  • Mile Road 30N, b/t 5E-6E
  • Mile Road 33N, b/t 1W-3W
  • Contractors working: 12
  • Pieces of equipment: 34
  • Urgent requests addressed: 3