August 27 – September 2, 2022 Progress

 

  • Sites worked on this week: 10, 14, 22, 23, 46, 59, 94, 97, 104, 115, 129, 132, 133, 143, 150, 151, 163, 174
  • Completed site:  89
  • Culvert sites repaired: 22, 23
  • Totals sites: 233
  • Ditches cleaned: 158.6 miles (90 ditch cleaning sites completed)
  • Roads temporarily graded: 68 Miles
    • Also regrading roads that were previously temporarily graded
  • Contractors working: 12
  • Pieces of equipment: 30
  • Urgent requests addressed: 3