August 27 – September 2, 2022 Progress
- Sites worked on this week: 10, 14, 22, 23, 46, 59, 94, 97, 104, 115, 129, 132, 133, 143, 150, 151, 163, 174
- Completed site: 89
- Culvert sites repaired: 22, 23
- Totals sites: 233
- Ditches cleaned: 158.6 miles (90 ditch cleaning sites completed)
- Roads temporarily graded: 68 Miles
- Also regrading roads that were previously temporarily graded
- Contractors working: 12
- Pieces of equipment: 30
- Urgent requests addressed: 3