October 22 – October 28, 2022 Progress
- Sites worked on this week: 29, 46, 61, 62, 77, 90, 91, 92, 98, 100, 102, 103, 104, 109, 126, 144, 147, 150, 151, 158, 177, 189, 193, 194, 203, 219, 220
- Completed site: See attached map
- Culvert sites repaired: 5
- Totals sites: 244
- Ditches cleaned: 190.375 miles
- Roads temporarily graded: 120 Miles
- Mile Road 2W, b/t 34N-36N
- Mile Road 26N b/t 3E-4E
- Mile Road 3E, b/t 26N-31N
- Mile Road 30N, b/t 3E-4E
- Mile Road 27N, b/t 2E-3E
- Mile Road 5E, b/t 26N-30N
- Mile Road 33N, b/t 1W-3W
- Mile Road 30N, b/t 5E-6E
- Mile Road 1E, b/t 28N-29N
- Contractors working: 12
- Pieces of equipment: 32
- Urgent requests addressed: 4