October 22 – October 28, 2022 Progress

  • Sites worked on this week: 29, 46, 61, 62, 77, 90, 91, 92, 98, 100, 102, 103, 104, 109, 126, 144, 147, 150, 151, 158, 177, 189, 193, 194, 203, 219, 220
  • Completed site:  See attached map
  • Culvert sites repaired: 5
  • Totals sites: 244

  • Ditches cleaned: 190.375 miles
  • Roads temporarily graded: 120 Miles
    • Mile Road 2W, b/t 34N-36N
    • Mile Road 26N b/t 3E-4E
    • Mile Road 3E, b/t 26N-31N
    • Mile Road 30N, b/t 3E-4E
    • Mile Road 27N, b/t 2E-3E
    • Mile Road 5E, b/t 26N-30N
    • Mile Road 33N, b/t 1W-3W
    • Mile Road 30N, b/t 5E-6E
    • Mile Road 1E, b/t 28N-29N
  • Contractors working: 12
  • Pieces of equipment: 32
  • Urgent requests addressed: 4

View map here.