July 25-29 2022 Progress
Ditch Cleaning was suspended from July 19 (Tues) to 21 (Thurs) due to landfills repair brought by heavy rains.
Sites worked on this week: 10, 12, 15, 27, 29, 51, 54, 53, 59, 60, 94, 177, 60, 69, 72, 73, 84, 88, 89, 90, 92, 109, 115, 121, 122, 129, 144, 164, 169, 172, 224, 225
Completed site: 80, 81, 175
Culvert sites repaired: None this week
Totals sites: 230
Ditches cleaned: 128.75 miles
Roads temporarily graded: 184.5 Miles:
- Mile Road 12E
- Mile Road 36N, east of 7E
- Mile Road 36N, east of 6E
- Mile Road 7W, north of 20N
- Mile Road 6E, south of 34N
- Mile Road 36N, west of 3E
- Mile Road 2E
- Mile Road 2W, south of PTH23
- Mile Road 1E, south of PTH23
- Mile Road 7E, south of 34N
- Mile Road 29N, west of 1E,
- Mile Road 30N, west of 1E
- Mile Road 31N, west of 1W
- Mile Road 2W, north of PR205
- Mile Road 34N, east of 1E
- Mile Road 2E, north and south of 33N
- Mile Road 32N, east and west of PR330
- Mile Road 6E, south of 30N
- Mile Road 7E, south of PR205
- Mile Road 32N, east of 6E
- Mile Road 3E, south of PR205
- Mile Road 28N, east and west of PR422
- Mile Road 33N, east of 6E
- Mile Road 30N, east and west of PR422
- Mile Road 30N, west of 1W
- Mile Road 1W, south of 30N,
- Mile Road 9W, south of 27N,
- Mile Road 9W, north of 26N
- Mile Road 10W, north and south of 25N
- Mile Road 26N, west of 7W
- Mile Road 26N, west of PR332
- Mile Road 7W, north of 29N
- Mile Road 8W, north of 29N
Contractors working: 18
Pieces of equipment: 39
Urgent requests addressed: 1
EMO assessed 52 sites this week (30 still remaining)