DFA Application

27/07/2022

If you have flood damage to claim, be sure to claim it before the application deadline. If you have not already done so, apply using the form below: https://rmofmorris.ca/wp-content/uploads/2022/05/dfaapplication-1.pdf


July 16-22 2022 Flood Rehabilitation Progress Report

25/07/2022

Ditch Cleaning was suspended from July 19 (Tues) to 21 (Thurs) due to landfills repair brought by heavy rains. Sites worked on this week: 10, 51, 59, 69, 80, 81, 82, 88, 89, 112, 122, 136, 145, 177, 213    Completed site:   None this week Culvert sites repaired: 2 – Site 112, 145 Totals sites: […]


July 9-15 2022 Flood Rehabilitation Progress Report

15/07/2022

Sites worked on this week: 15, 51, 54, 69, 84, 88, 93, 111, 112, 118, 122, 144, 145, 147 Completed site: 9 Totals sites: 229 Ditches cleaned: 93.875 miles